Bowling Group Northland New Zealand

Steve Bowling Contracting | SSP Engineering | NPM Remediation |
NPM Construction | GHK Piling |

  • Home
  • About Us
  • Our Team
  • Business Units
    • Steve Bowling Contracting
    • SSP Engineering
    • NPM Remediation
    • NPM Construction
    • GHK Piling
  • Projects
  • Compliance
  • Contact Us
You are here: Home » Steve Bowling Contracting » One Riverside Apartments

One Riverside Apartments

Site works, Structural Concrete & Masonry

Steve Bowling Contracting Ltd were contracted to carry out a Site works, Structural Concrete & Masonry Package on the One Riverside Apartments.  We were engaged as a subcontractor to NPM Construction who were the head contractor on the project. Our sub-contract works included:

  • Site excavation
  • Temporary shoring / retaining
  • Excavations of foundations
  • Floor slabs – ground floor foundations, first floor & second floor
  • Insitu poured columns & beams
  • Rib & infill and Unispan placement
  • Insitu veranda beam & column pouring
  • Block & infill of 2 levels of building, 3 levels of the lift well & veranda columns.

This project demonstrates where the civil construction industry interfaces with traditional building construction, and how the skills can be applied in this application.

The main challenge of this project has been the site & location. The block of 8 apartments takes up nearly the whole site so there has been so room on site for vehicle parking, deliveries or machinery. The location is bordered by 3 roads, one of which is 4 lanes & has a constant flow of heavy traffic.

Steve Bowling Contracting Limited were involved in the design phase of this project & were able to offer value engineering to the client. The method of using blocks & smaller items on site meant that we were able to minimise the amount of craneage required and therefore minimised road closures (and cost associated with traffic management) & other disruptions.

Our subcontract works were completed in approximately 3 weeks ahead of our programme.  The works were completed with no variations and under budget which was an achievement on a cost reimbursable form of contract.

  • IMG_0031
  • IMG_0036
  • IMG_0792
  • 1
  • 2
  • 3
  • DAN_4591-Edit

Phone: (09) 435 2119
Fax: (09) 435 2469
9-11 Hewlett Street, Whangarei
Email Us

KEY PERSONNEL

Dean Collinson, General Manager
Ben Bowling, Construction Supervisor
Steve Bowling, Managing Director
Cameron Lornie, Projects Engineer
Brett Snell, Construction Supervisor

Recent Projects

Riverside One Apartments

One Riverside Apartments

Tarewa Park Wastewater Storage Tanks

Tarewa Park Wastewater Storage Tanks

Whau Valley Retaining Wall

Whau Valley Retaining Wall

More Projects...

What Our Customers Say

  • ““To their credit, the staff of Steve Bowling Contracting worked with the MOE/School (and specific student’s needs), the design team and us as project managers to deliver a project we are all immensely proud of.” Trevor Griffiths – Director, Griffiths and Associates, May 2015 Read more...
  • “The project was completed on time and the playing surface has been well received by our hockey community...” Grant McLeod – CEO, Northland Hockey Association – 30 October 2015Read more...
  • "I just want to say how happy we are with the job you did. We were impressed with the way the guys worked and presented themselves on the job and how they were prepared to deal with my requests during it." Wayne McKeanRead more...

Contracting Services

  • Reinforced Concrete Structures
  • Precast Installation and Erection
  • Concrete Driveways
  • Concrete Repairs
  • Demolition
  • Site Works, Excavation and Drainage Services
  • Retaining Walls
  • Bridge Construction, Upgrades and Repairs
  • Guardrails
  • Specialist Industrial Coating and Epoxy Systems
  • Industrial Shutdowns
  • Seismic Upgrades & Strengthening

Systems & Compliance

Bowling Infrastructure Group considers it imperative that all staff return home to their families fit and healthy at the end of each day, the impact of our works on the environment is minimised, and that our projects are constructed to specification, … More info...

Business Units

  • Steve Bowling Contracting
  • SSP Engineering
  • NPM Remediation
  • NPM Construction
  • GHK Piling

© Copyright 2015 Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei · Login

Copyright © 2025 · Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei, 0110 · Email Us · Website Managed By Honey Pot Digital · Log in