Bowling Group Northland New Zealand

Steve Bowling Contracting | SSP Engineering | NPM Remediation |
NPM Construction | GHK Piling |

  • Home
  • About Us
  • Our Team
  • Business Units
    • Steve Bowling Contracting
    • SSP Engineering
    • NPM Remediation
    • NPM Construction
    • GHK Piling
  • Projects
  • Compliance
  • Contact Us
You are here: Home » Steve Bowling Contracting » Kirikopuni Bridge

Kirikopuni Bridge

Kirikopuni Bridge Upgrade was a contract to replace structural steel components to the trusses under the bridge, along with the replacement of rivets & other associated components.

The works involved provision of full scaffold access to the truss, removal of and treatment of corrosion at the sides of the deck support beams at deck joints (83 locations), replacement of corroded sections of bearing areas of the Steel “I” beams (16 locations), replacement of existing sections of corroded/deteriorated steel plate (20 locations), Replacement of deteriorated rivets with high strength friction grip bolts (128 locations), treatment of surface corrosion on all truss members and steel beams surfaces (this has effectively been a repaint of the whole bridge) and deck joint replacements (3 joints), Bridge deck cleaning and sealing.

One of the most challenging aspects of this job was to manage all of the environmental risks. The bridge is located over a large viaduct of native bush and a fresh water stream so the risk of contamination or pollution was extremely high.

Another challenge was the location and access to the bridge. Not only was it located in a remote part of Northland with no material distributors nearby, it was also hard to get any materials or goods on site because of the access. The whole bridge had to be scaffolded to gain access to the areas that required work so getting materials and machinery out on the scaffolded platforms was often a challenge.

Working from a scaffold at a height of approximately 25m above the ground at the highest point, meant all staff & sub-contractors on site had to have appropriate training for working at heights.

The bridge is an iconic structure in Northland and the need to protect all the historic aspects of this bridge was huge. We needed to make sure that the work we did to the bridge, fitted into the aesthetics of the original structure.

The existing lead based paint had to be removed from parts of the bridge being repaired and then repainted with a new coat of paint. This meant that staff had to be specially geared up to deal with the toxic chemicals and to make sure that they were transported and disposed of in approved methods.

The completion of the current works will mean that the bridge will not require any major maintenance for at least the next 25 -30 years.

  • 012
  • IMG_9203
  • IMG_9232
  • IMG_9283

Phone: (09) 435 2119
Fax: (09) 435 2469
9-11 Hewlett Street, Whangarei
Email Us

KEY PERSONNEL

Dean Collinson, General Manager
Ben Bowling, Construction Supervisor
Steve Bowling, Managing Director
Cameron Lornie, Projects Engineer
Brett Snell, Construction Supervisor

Recent Projects

Riverside One Apartments

One Riverside Apartments

Tarewa Park Wastewater Storage Tanks

Tarewa Park Wastewater Storage Tanks

Whau Valley Retaining Wall

Whau Valley Retaining Wall

More Projects...

What Our Customers Say

  • ““To their credit, the staff of Steve Bowling Contracting worked with the MOE/School (and specific student’s needs), the design team and us as project managers to deliver a project we are all immensely proud of.” Trevor Griffiths – Director, Griffiths and Associates, May 2015 Read more...
  • “The project was completed on time and the playing surface has been well received by our hockey community...” Grant McLeod – CEO, Northland Hockey Association – 30 October 2015Read more...
  • "I just want to say how happy we are with the job you did. We were impressed with the way the guys worked and presented themselves on the job and how they were prepared to deal with my requests during it." Wayne McKeanRead more...

Contracting Services

  • Reinforced Concrete Structures
  • Precast Installation and Erection
  • Concrete Driveways
  • Concrete Repairs
  • Demolition
  • Site Works, Excavation and Drainage Services
  • Retaining Walls
  • Bridge Construction, Upgrades and Repairs
  • Guardrails
  • Specialist Industrial Coating and Epoxy Systems
  • Industrial Shutdowns
  • Seismic Upgrades & Strengthening

Systems & Compliance

Bowling Infrastructure Group considers it imperative that all staff return home to their families fit and healthy at the end of each day, the impact of our works on the environment is minimised, and that our projects are constructed to specification, … More info...

Business Units

  • Steve Bowling Contracting
  • SSP Engineering
  • NPM Remediation
  • NPM Construction
  • GHK Piling

© Copyright 2015 Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei · Login

Copyright © 2025 · Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei, 0110 · Email Us · Website Managed By Honey Pot Digital · Log in