Bowling Group Northland New Zealand

Steve Bowling Contracting | SSP Engineering | NPM Remediation |
NPM Construction | GHK Piling |

  • Home
  • About Us
  • Our Team
  • Business Units
    • Steve Bowling Contracting
    • SSP Engineering
    • NPM Remediation
    • NPM Construction
    • GHK Piling
  • Projects
  • Compliance
  • Contact Us
You are here: Home » Steve Bowling Contracting » Hatea Loop Jetty Refurbishment

Hatea Loop Jetty Refurbishment

This contract was with Whangarei District Council for the refurbishment of the existing jetty on the Hatea Loop, a popular walking, running and cycling track. The works involved pile driving, demolition of some of the walkway and jetty, decking, kerbing, handrailing and other works. All of this was to be managed while ensuring the access to the Hatea Loop wasn’t compromised. Two of the existing dolphin structures were retained to preserve a bit if the heritage of the jetty.

The main challenge of this project was the limited access to the site. We had to crane some of the materials into the site from adjacent properties as the site access was too narrow.  This was done at early hours of the morning to minimise disruption and spotters were used to ensure the public safety was not compromised.   We were also working in a tidal environment which could not be accessed by piling equipment from land, which meant we drove the new piles off a barge, but the times available to have the barge on site was determined by the high tide. We used a pontoon to access the jetty when installing the timber headstocks and bearers.

The existing structure turned out to be slightly different layout to the design that was completed by the engineers (as the pile locations were not surveyed) so we had to redesign some components to make sure the structure was square when complete.

The most innovative part of this project was using the dredging barge to allow us to drive the piles.  We were able to pitch the 16m long piles with the long reach dredging excavator which was at one end of the barge and pull the piles down far enough into the silt to allow us to get our pile driving equipment over the top of the piles for driving.  Once the piles were pitched and safely secured in the ground we spun the barge around so that our pile driving equipment on the other end of the barge could be used.  This methodology allowed the works to be completed with minimal disruption to the public and was far less intrusive than building temporary staging to access from land.

Steve Bowling Contracting Ltd is dedicated to ensuring quality performance standards are upheld on all projects within the competitive construction industry, with this project being no exception.  The completed structure was finished with great attention to detail and the structure is certainly a feature of the ‘loop walk’.

  • IMG_4347
  • IMG_4360
  • IMG_4362

Phone: (09) 435 2119
Fax: (09) 435 2469
9-11 Hewlett Street, Whangarei
Email Us

KEY PERSONNEL

Dean Collinson, General Manager
Ben Bowling, Construction Supervisor
Steve Bowling, Managing Director
Cameron Lornie, Projects Engineer
Brett Snell, Construction Supervisor

Recent Projects

Riverside One Apartments

One Riverside Apartments

Tarewa Park Wastewater Storage Tanks

Tarewa Park Wastewater Storage Tanks

Whau Valley Retaining Wall

Whau Valley Retaining Wall

More Projects...

What Our Customers Say

  • ““To their credit, the staff of Steve Bowling Contracting worked with the MOE/School (and specific student’s needs), the design team and us as project managers to deliver a project we are all immensely proud of.” Trevor Griffiths – Director, Griffiths and Associates, May 2015 Read more...
  • “The project was completed on time and the playing surface has been well received by our hockey community...” Grant McLeod – CEO, Northland Hockey Association – 30 October 2015Read more...
  • "I just want to say how happy we are with the job you did. We were impressed with the way the guys worked and presented themselves on the job and how they were prepared to deal with my requests during it." Wayne McKeanRead more...

Contracting Services

  • Reinforced Concrete Structures
  • Precast Installation and Erection
  • Concrete Driveways
  • Concrete Repairs
  • Demolition
  • Site Works, Excavation and Drainage Services
  • Retaining Walls
  • Bridge Construction, Upgrades and Repairs
  • Guardrails
  • Specialist Industrial Coating and Epoxy Systems
  • Industrial Shutdowns
  • Seismic Upgrades & Strengthening

Systems & Compliance

Bowling Infrastructure Group considers it imperative that all staff return home to their families fit and healthy at the end of each day, the impact of our works on the environment is minimised, and that our projects are constructed to specification, … More info...

Business Units

  • Steve Bowling Contracting
  • SSP Engineering
  • NPM Remediation
  • NPM Construction
  • GHK Piling

© Copyright 2015 Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei · Login

Copyright © 2025 · Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei, 0110 · Email Us · Website Managed By Honey Pot Digital · Log in