Bowling Group Northland New Zealand

Steve Bowling Contracting | SSP Engineering | NPM Remediation |
NPM Construction | GHK Piling |

  • Home
  • About Us
  • Our Team
  • Business Units
    • Steve Bowling Contracting
    • SSP Engineering
    • NPM Remediation
    • NPM Construction
    • GHK Piling
  • Projects
  • Compliance
  • Contact Us
You are here: Home » Steve Bowling Contracting » Diggers Valley Road Bridge

Diggers Valley Road Bridge

This project for Far North District Council involved the removal and replacement of 2 precast bridge deck units on Bridge D21 and 6 units on bridge D22 on Diggers Valley Road between Broadwood and Kaitaia.  The contracts for the manufacture and installation were let separately purely to allow us to commence manufacture promptly.  The first contract was the off-site manufacture of the precast reinforced concrete bridge deck units.  The second contract involved the removal of the existing deteriorated units, demolition and rebuild of the abutment back walls to match the new panels and the installation of the new bridge units, bridge jointing and installation of guardrail / railing.

The construction of the panels was difficult because they had to be made to fit an existing bridge.  Prior to commencement of manufacture we went to site with the drawings to ensure that all dimensions, interfaces, connections and details were thought about as getting the manufacture of the panels correct would ensure the installation works would also be successful.

We had to re-build the existing deteriorated abutment back walls, and to match to the new bridge panels which were slightly thicker than the existing ones.  Getting the abutment back walls constructed in the correct locations were critical, as the panels had only a 6mm gap between each other to allow for expansion and contraction.

The biggest challenge that we faced was that we were unable to close the bridge fully throughout the works as there was no suitable detour route & we needed to maintain access for residents (and the school bus which used the route daily). We were able to complete the abutment back wall demolition and reconstruction and other preparatory works whilst keeping the road open under traffic management and using roadway cover plates as a temporary measure to allow a safe passage for vehicles.  After liaison with stakeholders we were able to implement a two-week road closure during the school holidays to allow the bridge panels to be removed and reinstalled.  This provided significant health and safety benefits and also ensured productivity on the installation works.  The road was re-opened 4 days ahead of schedule.

The project was successfully completed in May 2018 ahead of schedule and the road closure minimised.  The road was scheduled to be closed for 12 days however due to the fact we were able to allocate additional personnel on site, undertake long days and we had a window of favourable weather conditions for installation of the panels, we were able accelerate the programme and reopen the road 4 days ahead of schedule.

The project was completed on budget and the variations for the project were negative (saving for the client by substituting materials).

  • IMG_6100
  • IMG_6757
  • 20180406_085712
  • IMG_6686

Phone: (09) 435 2119
Fax: (09) 435 2469
9-11 Hewlett Street, Whangarei
Email Us

KEY PERSONNEL

Dean Collinson, General Manager
Ben Bowling, Construction Supervisor
Steve Bowling, Managing Director
Cameron Lornie, Projects Engineer
Brett Snell, Construction Supervisor

Recent Projects

Riverside One Apartments

One Riverside Apartments

Tarewa Park Wastewater Storage Tanks

Tarewa Park Wastewater Storage Tanks

Whau Valley Retaining Wall

Whau Valley Retaining Wall

More Projects...

What Our Customers Say

  • ““To their credit, the staff of Steve Bowling Contracting worked with the MOE/School (and specific student’s needs), the design team and us as project managers to deliver a project we are all immensely proud of.” Trevor Griffiths – Director, Griffiths and Associates, May 2015 Read more...
  • “The project was completed on time and the playing surface has been well received by our hockey community...” Grant McLeod – CEO, Northland Hockey Association – 30 October 2015Read more...
  • "I just want to say how happy we are with the job you did. We were impressed with the way the guys worked and presented themselves on the job and how they were prepared to deal with my requests during it." Wayne McKeanRead more...

Contracting Services

  • Reinforced Concrete Structures
  • Precast Installation and Erection
  • Concrete Driveways
  • Concrete Repairs
  • Demolition
  • Site Works, Excavation and Drainage Services
  • Retaining Walls
  • Bridge Construction, Upgrades and Repairs
  • Guardrails
  • Specialist Industrial Coating and Epoxy Systems
  • Industrial Shutdowns
  • Seismic Upgrades & Strengthening

Systems & Compliance

Bowling Infrastructure Group considers it imperative that all staff return home to their families fit and healthy at the end of each day, the impact of our works on the environment is minimised, and that our projects are constructed to specification, … More info...

Business Units

  • Steve Bowling Contracting
  • SSP Engineering
  • NPM Remediation
  • NPM Construction
  • GHK Piling

© Copyright 2015 Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei · Login

Copyright © 2025 · Bowling Infrastructure Group, 9-11 Hewlett Street, Port Whangarei, 0110 · Email Us · Website Managed By Honey Pot Digital · Log in